Data date: 4 November 2026 (24 Jumada I 1448 AH)
7 live projects, the portfolio is 1.8% behind baseline
- Contract value in progress
- SAR 1,146.5M
- Earned value
- SAR 423.6M
- Actual cost
- SAR 427.5M
- Schedule index SPI
- 0.96
- Cost index CPI
- 0.99
Values come from executed quantities in certified payment certificates and cost entries in each project's analytic account.
- Baseline
- Actual
- Forecast
Project register
P-2304, Jeddah
SAR 212.4M
Actual cost of budget42.3%Yellow tick: earned value (41.0%)
SPI 0.87CPI 0.97High riskGlazing shop drawings awaiting consultant approval for 3 weeks
P-2309, Jeddah
SAR 96.8M
Actual cost of budget80.4%Yellow tick: earned value (74.0%)
SPI 0.94CPI 0.92High riskMedical gas variation unapproved; ductwork cost overrun
P-2402, NEOM region
SAR 122.0M
Actual cost of budget12.0%Yellow tick: earned value (12.0%)
SPI 0.89CPI 1.00Medium riskRock excavation quantities exceed the BOQ by 18%
P-2301, Riyadh
SAR 148.6M
Actual cost of budget60.8%Yellow tick: earned value (62.0%)
SPI 0.95CPI 1.02Medium riskStructural steel for School C roof is two weeks late
P-2311, NEOM region
SAR 184.5M
Actual cost of budget33.7%Yellow tick: earned value (35.0%)
SPI 0.99CPI 1.04Low riskPrecast deliveries running to schedule
P-2312, Riyadh
SAR 64.2M
Actual cost of budget88.9%Yellow tick: earned value (88.0%)
SPI 1.01CPI 0.99Low riskChiller 3 commissioning tests scheduled next week
P-2307, Riyadh
SAR 318.0M
Actual cost of budget27.7%Yellow tick: earned value (28.0%)
SPI 1.04CPI 1.01Low riskNo critical issues, level 7 slab in progress